Ferntree Ridge – July 2019 Construction Update

Ferntree Ridge has been a hive of activity over the past few months with construction of new stages nearing completion and the first homes starting to be built. Below is a summary of construction works at Ferntree Ridge.

Stage 1
• Only one lot remaining for sale
• Construction of stage is complete with roads open
• Display Village building as commenced with many of our builders starting work on their beautiful display homes.
• Electricity has been connected
• Gas has been connected
• Street trees have been planted
• Titles have been released

Stage 2
• Only 10 lots remaining
• Construction of stage is complete with roads open
• Electricity has been connected
• Street trees have been planted
• Titles have been released

Stage 3
• Construction is complete
• Titles are due by 31st August
• Power connection has been ordered
• Roads soon to be opened to the public

Stage 4
• Construction is almost complete
• Titles are due by 30th September

Stage 5
• Construction is underway
• Asphalt is due to go down at the start of September
• Titles expected around the end of October

To view land currently available at Ferntree Ridge visit:
www.landgipps.com.au/land-for-sale/

To view house and land packages available at Ferntree Ridge visit:
www.landgipps.com.au/house-and-land/

Enquire about this lot

"*" indicates required fields

This field is for validation purposes and should be left unchanged.
This field is hidden when viewing the form
This field is hidden when viewing the form
This field is hidden when viewing the form